AEP Rockport Station River Cells 31 and 32

Notice Number: 2023 - 010
Date: June 28, 2023 through September 15, 2023,

Notice is given that “Richard Goettle, Inc.” will be replacing existing river cells 31 and 32 with new 22-foot diameter river cells along the same berthing line. Hours of operation will be June 28, 2023 through September 15, 2023, Monday through Saturday 7:00 am. to 6:00 pm Central Time.

The contractor’s floating plant will consist of one 120’x 54.5’ spud barge with 250 Ton crawler crane and 180’ boom, and two 195’x 35’ material flat barges carrying materials and small equipment.

Later in the project, the floating plant will additionally have a 195’x 35’ hopper barge carrying coarse aggregate. VHF Marine channels 66 and 67 will be monitored.

/s/
Shawn Kenney
Chief, Technical Support Branch