Black Warrior Tombigbee Waterway, Alabama Lock Closure Holt Lock & Dam River Mile 347

Notice Number: 214669-1 / 26-90
Effective: 07/16/2026 14:00 thru 07/16/2026 15:00 CDT

Reference to Navigation Bulletin 26-88

Notice is given to mariners that Holt Lock (River Mile 347) will be periodically closed and operate under a modified schedule starting Monday, 12 January 2026 to perform repairs on a damaged lock monolith. The modified lock operation schedule will be as follows:

• Closed to navigation 0600 Mondays to 0600 Saturdays

• Open to navigation 0600 Saturdays to 0600 Mondays

Update: Holt lock is now closed to navigation. See table below for remaining schedule for the repairs and major activities:

Start   End   Task
13-Jul   10-Sep   Closure 1 (60-day)
11-Sep   1-Oct   Lock open 24/7 for traffic
2-Oct   26-Oct   Closure 2 (25-day)
27-Oct   6-Nov   5/2 schedule

Due to the nature of this construction, dates are subject to change. If changes are required, USACE will communicate any schedule changes with industry through future navigation bulletins and waterway users calls.

A waterway users call is scheduled for 16 July 2026 at 1400 CDT to provide information regarding the closure. Join on your computer, mobile app, or room device:

https://dod.teams.microsoft.us/l/meetup join/19%3adod%3ameeting_f9018ce4ec7c4041b0bcec62981eb390%40thread.v2/0?context=%7b%2 2Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22e202419e 62cd-4af1-9259-598613bb5a3d%22%7d

Or call in (audio only):

Dial-in Number: (503) 207-9433

Conference ID: 147 626 433#

For further information regarding this work, please contact Holt Lock at (251) 276-3293, or Mr. Chad Brumelow at the BWT/Alabama-Coosa Project Management Office at (205) 752-3571.

//signed//
Green, Ryan A