Bridge 631 Indiana Harbor

Good morning,

For those who transit Indiana Harbor over in Whiting to BP, I was just on a call with the USCG Bridge Branch and CN Railroad to discuss the closures at the bridge site to pass rail traffic. See below for topics discussed.

Below is a recurring meeting invitation beginning tomorrow to discuss the bridge operations schedule.

I recognize this is short notice and understand that not everyone may be able to attend, particularly tomorrow. I also understand that the recurring meeting time may not work for everyone. We will use these meetings to stay aligned on the schedule and address any questions as they arise.

The current bridge operations schedule is as follows:

Bridge Operations: 24-hour period, twice per week, for 30 weeks

  • Monday at Noon through Tuesday at Noon
  • Thursday at Noon through Friday at Noon

This closure started this past Monday 9/21/26 and is projected to continue until Friday 12/18/26. There will be a railroad rep on site monitoring ch 16 and will announce when the channel will be blocked and when they reopen it. We will meet every Wednesday morning until they are done to discuss any updates or changes and I will get those out to everyone as soon as I can. If you have any question please let me know and I will try and get answers.

Thanks

Per email from Terry Bass