Channel Maintenance Dredge USACE Dredge Potter Upper Mississippi River Mile 242.2
Notice Number: 215338-1
Effective: 10/22/2026 14:00 thru 10/23/2026 14:00 CDT
1. Commencing on Thursday, 22 October 2026 at 1400 and continuing for 24 hours until Friday, 23 October 2026 at 1400, the navigation channel will be closed at the upper approach to Lock and Dam 25 (approximately River Mile 242.2) as the US Army Corps of Engineers Dredge Potter will be performing channel maintenance dredging. The closure is necessary due to the proximity of the lock and for increased efficiency in dredging.
2. This closure has been coordinated with RIAC and the US Coast Guard.
3. The Dredge Potter and its attendant plant, to include tender boats, small boats, barges and pipeline, etc., work 24 hours a day, 7 days a week. When dredging, removed river bottom material is pumped through a pontoon pipeline or self floating pipeline, which may be crossing the channel, and is placed outside of the navigation channel.
4. The USACE Dredge Potter can be contacted on Marine Channel 13 or 16.
5. For the latest updates, channel condition reports, and recent channel surveys, please visit
htttps://www.mvs.usace.army.mil/Missions/Navigation/
Amended to adjust dates and times.
FOR THE DISTRICT ENGINEER:
//signed//
Cox, Ashley N, Deputy Chief, Operations and Readiness Division