  1. The US Army Corps of Engineers Dredge Potter has resumed dredging operations as of 15 December 2021and will continuing until further notice. The Dredge Potter will perform channel maintenance dredging at various locations within the St. Louis District, Upper Mississippi River from mile 183 to 0 with the below schedule.
  1. The Dredge Potter is working at mile 173 UMR. The updated schedule, shown below, now includes a planned 24-hour river closure for work at mile 182.7 UMR that has been coordinated with the USCG and RIAC.  Updates to the schedule will be provided as work progresses.
    1. Mile 173, 2 days, 20-22 Dec 2021
    2. Mile 181, 1 day, 23 Dec 2021
    3. Mile 182.7, River closed for dredging at 5pm on 27 Dec thru 5pm on 28 Dec 2021.
    4. Mile 46.5, 7 days, 29 Dec - 4 Jan 2022
    5. Mile 110.5, 3 days, 5 - 7 Jan 2022
  1. The Dredge Potter and its attendant plant, to include tender boats, small boats, barges and pipeline, etc., work 24 hours a day, 7 days a week. When dredging, removed material is pumped through a pontoon pipeline or self-floating pipeline, which may be crossing the channel, and is placed outside of the navigation channel. Mariners should be on the lookout for tender boats, barges, small survey boats, and pipeline when transiting the dredge area.
  1. The Dredge Potter may be contacted on VHF-FM radio channels 13 and 16. Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made with the Dredge Potter.

FOR THE DISTRICT ENGINEER:

//signed//

Andrew C. Schimpf, P.E.
Rivers Project Manager