Completed Mississippi River Mechanical Dredging (Strike Removal): Linwood, UMR Mile 475.2-475.9

Notice Number: 201330-1/MR 22-201330-1
Date: 09/27/2022 06:00 thru 11/02/2022 17:00

Mechanical dredging (Strike Removal) operations will commence on Tuesday, 27-September-2022 and will continue until Further Notice at Linwood, UMR 475.2-475.9. Dredging will be performed 7 days per week, 12 hrs per day, 0600-1800.

Mariners are requested to contact the MV Laura K on channel 13 or 7, THIRTY minutes prior to transiting the area.

Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made.

//signed//

Jon Klingman
Chief, Channel Maintenance Section Operations Division