Cheatham Lock at Cumberland River Mile 148.7 will be closed to navigation beginning at 0600 16 May 2022 and continuing through 05 August 2022 due to repairs on upper gates and culvert valves. There will be temporary openings to allow navigation passage during the listed phases posted below. The USACE Light Capacity Fleet will be moored to the upper mooring cells throughout the duration of the project. During these temporary openings there will not be any restriction.
Task Name |
Duration |
Start |
Finish |
Phase 1 |
14 Days |
05/16/2022 |
05/29/2022 |
Lock Closed |
11 Days |
05/16/2022 |
05/26/2022 |
Lock Open |
3 Days |
05/27/2022 |
05/29/2022 |
Phase 2 |
14 Days |
05/30/2022 |
06/12/2022 |
Lock Closed |
11 Days |
05/30/2022 |
06/09/2022 |
Lock Open |
3 Days |
06/10/2022 |
06/12/2022 |
Phase 3 |
14 Days |
06/13/2022 |
06/26/2022 |
Lock Closed |
11 Days |
06/13/2022 |
06/23/2022 |
Lock Open |
3 Days |
06/24/2022 |
06/26/2022 |
Phase 4 |
14 Days |
06/27/2022 |
07/10/2022 |
Lock Closed |
4 Days |
06/27/2022 |
06/30/2022 |
Lock Open |
10 Days |
07/01/2022 |
07/10/2022 |
Phase 5 |
14 Days |
07/11/2022 |
07/24/2022 |
Lock Closed |
11 Days |
07/11/2022 |
07/21/2022 |
Lock Open |
3 Days |
07/22/2022 |
07/24/2022 |
Phase 6 |
11 Days |
07/25/2022 |
08/04/2022 |
Lock Closed |
11 Days |
07/25/2022 |
08/04/2022 |
Lock Open Project Complete |
08/05/2022 |