Dredge Update 28 December 2022
Attached is the updated dredge schedule for St. Louis District. The Dredge Potter is anticipated to start work at mile 181 tomorrow, pending favorable ice conditions. The Dredge Jadwin’s estimated arrival at mile 42 is on Monday.
Mile 24 has a potential to get added to the schedule, as it is showing less than 9-ft, 28 days out. The river will need to be 3-ft below LWRP for this location to be less than 9-ft and it’s just barely that on the 28 day forecast. Will keep an eye on this location, and re-evaluate next week if this location needs to be added to one of the dredges assignments.
//signed//
Lance