Dredging – Paducah Transient Boat Dock ORM 935

Notice Number: 2024-003
Date: January 18 thru March 1, 2024

Notice is given that “Dredge America, Inc” will commence maintenance dredging, via hydraulic dredging, to remove accumulated sediment within an 8.25-acre area (900 ft x 400 ft) around the transient boat dock along the Paducah Riverfront. The dredged material will be removed down to 2 feet above natural river bottom elevations. All dredged material to be discharged through a pipeline 3,550 feet downstream along the left descending bank of the Ohio River at River Mile 935.8.

The approximate schedule for this work will be January 18 – March 1, 2024. Mobilization work hours will be 8 hrs/day, Monday-Friday. Dredging work hours will be 24 hrs/day, 7 days/week. Demobilization work will be 8 hrs/day, Monday-Friday.

The Dredge will monitor Marine Channel 16.

/s/
Shawn Kenney
Chief, Technical Support Branch