Dredging Vicksburg Harbor
Notice Number: 212225
Effective: 10/13/2025 08:00 thru UNTIL FURTHER NOTICE CDT
1. The DREDGE NIMITZ is dredging at the Vicksburg Harbor.
2. The DREDGE NIMITZ and its attendant plant, to include tender boat, small boats, barges, pipelines, etc. work 24 hours a day, 7 days a week. When dredging, dredged material is pumped through a pipeline, which may be crossing the channel, and is placed outside of the navigation channel.
3. Passing arrangements can be made with the DREDGE NIMITZ by contacting them on VHF-FM radio channels 13 and 16. Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made with the DREDGE NIMITZ.
//signed//
Ross Buckley, Navigation Unit Chief