Duke Energy Aerial Power Line Replacement Ohio River Mile 491

Notice Number: 214569 / 2026-034
Effective: 07/13/2026 07:00 thru 07/19/2026 17:00 EDT

Par Electric, a contractor for Duke Energy, will be removing Aerial Power Lines which cross over the Ohio River at Mile 491. This work will occur 13-19 July 2026, 0700-1700 ET.

Navigation traffic impacts are expected to be minimal, as the work will be paused as needed to allow navigation traffic to pass with minimal delay, but there will be intermittent river closures to ensure marine safety.

A helicopter will be used to assist with the work. A safety boat will be on the river to enforce a USCG safety zone from Mile 490 through Mile 492 while the helicopter is working or while lines are not safely secured.

All navigation traffic shall make contact with the safety boat on Marine Channel 13 when transiting the area while work is occurring to coordinate safe passage.

//signed//
Kenney, Shawn M, Chief, Technical Support Branch