Gulf Intracoastal Waterway, Texas – Corpus Christi Bay to Port Isabel w/Channel to Harlingen Pipeline Dredging

Notice Number: 214969 / 214969_NTN-14_GI_CC-PI_CTH_2026-08
Effective: 09/04/2026 00:00 thru 04/07/2027 00:00 CDT

Dredge Ranger (contractor, Inland Dredging) will begin 24-hour dredging operations on or about 04 September 2026 on the Arroyo Colorado (Channel to Harlingen).

Dredging areas will be from the mouth of the Arroyo River to Rio Hondo (channel marker 20). Dredging will start near the mouth and proceed west towards the Port of Harlingen.

Contractor’s related floating plant (two supply barges, one anchor barge, one crane barge, fuel barge, and three tender boats) will be used in/around this work area. Dredge Ranger will have approximately 15,000 linear feet of pipe will be utilized extending to and placement of material in USACE approved upland placement areas.

The Dredge Ranger is requesting advance notification of passing vessels on VHF Channel 16 and 13, a slow bell when passing the work to minimize wake, no meeting or overtaking next to the dredge operations.
The Dredge can be reached by phone at 713-913-7205
Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution while passing.
Dredging operation will be 24 hrs., 7 days a week.

//unsigned//