Lagrange Lock queue assist plan
S/B locking-
When we are locking S/B in groups of 6 boats, the #1 and #2 boat in the 2nd S/B group will get together above Briggs. Depending on tows and configuration one of those boats in the 2nd group will come down to assist group 1 into the lock, Holding them flat on the wall and assisting as necessary for that group.
The #1 and #2 boat in the next N/B group will get together and send one of them to pull the #1 S/B cut.
#1 S/B boat in group 1 will lock through and tie off their S/B tow on the #1 N/B tow waiting below the lock. The S/B boat will go back light boat and pull the #2 S/B cut. Once they have remade the coupling the boat will return to their tow and head south. The #2 S/B boat will tie off on the #1 N/B tow and continue this until the last boat in the group is done locking.
Basically, you pull the cut of the tow behind you.
N/B locking-
When we are locking N/B, the S/B vessel that was assisting on the upper wall will stay and pull the #1 N/B cut then return to their tow.
The #1 N/B boat will tie off on #1 S/B tow and continue in the same way we did S/B, Pulling the cut of the boat behind you. Until the N/B group is completed, then switch back S/B and start this all over again.
Any questions contact your Port Captain.