LOCK AND DAM 25 DAMAGED PROTECTION CELL REMOVAL UPDATE 18 FEBRUARY 2026 Lock and Dam 25 Upper Mississippi River mile 241.4

Notice Number: 212499-2
Date: 11/14/2025 15:00 thru UNTIL FURTHER NOTICE CST

This update adds Friday, 27 February 2026 to the closure schedule.

USACE Contractor, Massman Construction Co. will begin removal of the Lock and Dam 25 damaged protection cell on 23 February 2026. For safe and efficient removal operations, Lock 25 will be closed for 12 hours on each of the following days.
February 23, 24, 25, 26, and 27 from 0600 to 1800 hours
March 9, 10, 11, 12, and 13 from 0600 to 1800 hours
The requirement for an assist vessel remains in place and until further notice, vessels will be required to use an assist vessel as not to land on the Protection Cell northbound or create excess wheel wash when exiting the Lock southbound.
All navigation interest should be alert for, and abide by, any special instructions that may be issued by the Lockmaster.
FOR THE DISTRICT ENGINEER:

//signed//

Andrew C. Schimpf, P.E., Rivers Project Manager