MCALPINE LOCKS & DAM PORTLAND CANAL WALL REPAIRS OHIO RIVER MILE 606.8
REFERENCE:
Navigation Notice # 2024 – 019 dated 27 June 2024
Navigation Notice # 2024 – 021 dated 3 July 2024
Navigation Notice # 2024 – 047 dated 7 October 2024
Navigation Notice # 2024 – 053 dated 12 November 2024
Navigation Notice # 2024 – 054 dated 25 November 2024
Navigation Notice # 2024 – 057 dated 20 December 2024
Navigation Notice # 2025 – 006 dated 13 March 2025
Navigation Notice # 2025 – 011 dated 24 March 2025
Navigation Notice # 2025 – 018 dated 28 April 2025
Summary of Changes: The contract for the Portland Canal Wall Repair has been extended to September 20, 2025. Also, the contractor has been authorized to work when VTS is activated, up to a 15’ on the McAlpine Upper Gage, during the 1000-1500 closure window.
McAlpine Locks and Dam (Ohio River Mile 606.8): The contractor will continue work on the Portland Canal Wall Repairs at the upstream end of the canal from June 24 to September 20, 2025, for up to 12 hours each day (Monday – Saturday).
Traffic Restrictions detailed below apply Monday thru Saturday, for 3 different river condition scenarios.
1. Normal Pool: Vessel Traffic Service (VTS) deactivated, Mcalpine Upper Gage < 13’
· 0700 -1000 ET: Only upbound traffic will be permitted
· 1000 -1500 ET: No traffic will transit the Portland Canal while diving activities are underway.
· 1500 -1900 ET: Only upbound traffic will be permitted
· 1900 - 0700 ET: Normal operations with upbound and downbound traffic will be permitted.
2. Moderately High Water: VTS activated, Mcalpine Upper Gage between 13’ and 15’
· 1000 -1500 ET: No traffic will transit the Portland Canal while diving activities are underway.
· 1500 - 1000 ET: Normal operations with upbound and downbound traffic will be permitted.
******* Note the shortened hours above, with only 5 hours per day *******
3. High Water: VTS activated, Mcalpine Upper Gage > 15’
· No contractor work in this river condition scenario and no traffic restrictions due to this repair project.
During work hours, the contractor will have a 52-foot-wide floating plant at the mouth of the canal moored at the site of repair. Outside of work hours, the contractor’s floating plant will be moored on the Indiana side of the channel just downstream of the L&I bridge, in the Portland Canal. The approximate locations described above are shown in the attached image. The floating plant will consist of a crane barge, excavator barge, motor vessel, two material barges, and dive/crew vessel.
All navigation traffic will be advised to proceed with caution while work is ongoing. Traffic shall take direction from McAlpine lock operators for all lockage procedures. Traffic shall contact the M/V Miss Linda for passing instructions on Marine Channel 14. Upbound traffic should initiate contact at the L&I Railroad Bridge prior to reaching the work site.
//signed//
Kenney, Shawn M, Chief, Technical Support Branch