Mechanical dredging update mile 194 – 17 August 2023

Notice Number: 203425-1/12-10A
Date: 08/11/2023 06:00 thru Until Further Notice

1. As of 17 August 2023, mechanical dredging at mile 194 UMR is suspended due to repairs needed with the excavator. Repairs are estimated to be complete on Monday, 21 August 2023, and mechanical dredging is expected to resume work at mile 194 as early as Monday afternoon.

2. An NTNI update will be provided when mechanical dredging resumes work.

FOR THE DISTRICT ENGINEER:

//signed//

Andrew C. Schimpf, P.E.
Rivers Project Manager