Navigation Notice 207255 Scheduled Winter Closures Locks 27 Main, Melvin Price Main, Lock 25

SCHEDULED WINTER LOCK CLOSURES
Locks 27 Main Lock, Melvin Price Main Lock, Lock 25
Upper Mississippi River mile 185.5, 200.5, and 241.4

1. Winter closures at the following Locks are scheduled with the anticipated reopening dates shown.

a. Mel Price Main Lock: 1 Jan thru 1 Apr, 90 days, Phase III (final) replacement of the upstream liftgate.

b. Locks 27 Main Lock: 1 Jan thru 1 Apr, 90 days, replacement/repairs to embedded metals.

c. Lock 25: 1 Jan – 2 Mar, 60 days, installation of downstream sill beam and repairs to guidewall concrete.

2. All navigation interest should be alert for, and abide by, any special instructions that may be issued by the Lockmaster.

FOR THE DISTRICT ENGINEER:

//signed//

Andrew C. Schimpf, P.E.,
Rivers Project Manager