Navigation Notice: Cumberland River

Permanent Lower Dock Barge Construction
LaFarge-Holcim Facility
Cumberland River Mile 7.2 RDB

 

NOTICE NUMBER: 19187 / 22-04
EFFECTIVE: 02/01/2022 10:51 thru 06/30/2022 10:51 CDT

 

Sterling Industrial will be conducting the final installation of the permanent lower dock barge at the Lafarge-Holcim facility at Cumberland River Mile 7.2 RDB. This project began operation on 1 February 2022 and is estimated to be complete on 30 June 2022. During this time, there will be several barges in the water (a 110’ x 51’ crane barge and a 100’ x 30’ material barge). After working hours, the barges will be moored at the down-river end of the new lower dock barge. The crews will be monitoring Marine Channels 13 and 78.

 

//signed//