Navigation Notice: Cumberland River

Cheatham Lock 2022 Lock Closure Schedule
There will be no restrictions during the temporary openings

 

NOTICE NUMBER: 19246 / 22-11
EFFECTIVE: 05/16/2022 10:04 thru 08/05/2022 10:04 CDT

 

Cheatham Lock at Cumberland River Mile 148.7 will be closed to navigation beginning at 0600 16 May 2022 and continuing through 05 August 2022 due to repairs on upper gates and culvert valves. There will be temporary openings to allow navigation passage during the listed phases posted below.  During these temporary openings there will not be any restriction.

 

Task Name Duration Start Finish
Phase 1 14 Days 05/16/2022 05/29/2022
Lock Closed 11 Days 05/16/2022 05/26/2022
Lock Open 3 Days 05/27/2022 05/29/2022
Phase 2 14 Days 05/30/2022 06/12/2022
Lock Closed 11 Days 05/30/2022 06/09/2022
Lock Open 3 Days 06/10/2022 06/12/2022
Phase 3 14 Days 06/13/2022 06/26/2022
Lock Closed 11 Days 06/13/2022 06/23/2022
Lock Open 3 Days 06/24/2022 06/26/2022
Phase 4 14 Days 06/27/2022 07/10/2022
Lock Closed 4 Days 06/27/2022 06/30/2022
Lock Open 10 Days 07/01/2022 07/10/2022
Phase 5 14 Days 07/11/2022 07/24/2022
Lock Closed 11 Days 07/11/2022 07/21/2022
Lock Open 3 Days 07/22/2022 07/24/2022
Phase 6 11 Days 07/25/2022 08/04/2022
Lock Closed 11 Days 07/25/2022 08/04/2022
Lock Open Project Complete 08/05/2022

 

 

 

//signed//