Norrell Lock (No.1) NM 10.3 Closure Update (MKARNS)
Notice Number: 201669/SWL 22-67
Date: 12/01/2022 00:00 thru UNTIL FURTHER NOTICE
The current work schedule for the Lock 1 stoplog slots project has been revised as shown below. The 70’ width restriction is expected to be lifted on December 7. If the scheduled dates change, an updated navigation notice will be issued. An additional full lock closure will take place at the end of the project in order for the new closure system to be tested; the specific dates will be provided in a subsequent navigation notice.
Lock 1 schedule:
Dec 1 – Jan 20: Full Closure, 7 a.m. – 7 p.m. daily
Lock Open: 7:01 p.m. – 6:59 a.m. nightly (70’ width restriction –until Dec 7)
Questions or requests for additional information concerning this notice should be directed to the Little Rock District Office at (501) 324-5096 or you may email CESWL-OP-OM@usace.army.mil.
//signed//
Christopher B. Roark
Deputy Chief, Operations Division