Notice to Navigators: Missouri River

Kansas City 24 Nov 2021 - River Operations Update

 

  1. Survey – Survey crews are off for rest of week. Teams have completed more than 325 surveys this year. Scheduled to start with RM 26 next week.
  2. USACE KC Floating Plant – Monday will resume loading rock at Lexington, MO and working at RM 280.
  3. WA Ellis –  Moving toward Glasgow, MO RM 226.
  4. Newt Marine
    1. Plant 1 – Moving toward RM 8.
    2. Plant 2 – Working RM 120 – 140 reach.
  5. Flow support schedule to reduce started reducing releases. Weekly update is attached. Scheduled to reach target release of 12 kcfs on or about 8 Dec.
  6. Misc – NWS Sioux City and Omaha gages prediction attached. This shows flows starting to reduce.

 

 

Next update Monday 29 Nov.

 

J Rudy