Notice to Navigators: Red River

Red River Navigation Update & Lock Closures

 

Please click here to view the USACE slides regarding the Lindy C Boggs L & D and Red River L & D 1.

 

Navigation Status

* The pools are experiencing a minor rise that should not impact navigation between Locks.

* ACME is at 27.3' and rising to 28.3' by Sunday, 6 March.

* Red River Landing is at 45.5' and projected to crest at 49.0' on Saturday, 12 March.

 

Old River Lock Major Maintenance

* At this time Old River Lock plans on closing on 15 August 2022 for 90 days.

* There is no opportunity for intermittent openings during this closure.

 

Red River Lock 1 Major Maintenance (attached is a Lock 1 briefing)

* Lock 1 will be closed for 60 days during the 90-day Old River Lock closure.

 

Industry Input

* Access to the Mississippi River, through Old River Lock will be closed for 90 days.

* Industry needs to consider stockpiling product.

* There is an alternate route, around Old River Lock, by the Atchafalaya River.

* Vicksburg District is considering opening Lock 1 during the 60-day closure to pass traffic.

* Industry needs to consider the option of Lock 1 closed for 30 days, open for 1-2 weeks and closed for 30 days - BUT would have to use the Atchafalaya River. We will be requesting impacts and industry input in April.

 