Notice to Navigators: Upper Mississippi River

CHANNEL MAINTENANCE DREDGING - UPDATE 15 December 2021
USACE Dredge Potter
Upper Mississippi River mile 183 - 0 

 

Notice Number: 17708/ 14754-8
Effective Date: 07/09/2021 08:00 thru 01/31/2022 23:59 CST

 

  1. The US Army Corps of Engineers Dredge Potter has resumed dredging operations as of 15 December 2021and will continuing until further notice. The Dredge Potter will perform channel maintenance dredging at various locations within the St. Louis District, Upper Mississippi River from mile 183 to 0 with the below schedule. Updates will be provided as work progresses.
    1. Mile 171, 7 days, 15-21 Dec.
    1. Mile 173, 2 days, 22-23 Dec
    1. Mile 181, 1 day, 27 Dec
    1. Mile 182.7, 1 day, 28 Dec (24 hour river closure will be requested)
    1. Mile 46.5, 7 days, 29 Dec - 4 Jan
  1. The Dredge Potter and its attendant plant, to include tender boats, small boats, barges and pipeline, etc., work 24 hours a day, 7 days a week. When dredging, removed material is pumped through a pontoon pipeline or self-floating pipeline, which may be crossing the channel, and is placed outside of the navigation channel. Mariners should be on the lookout for tender boats, barges, small survey boats, and pipeline when transiting the dredge area.
  1. The Dredge Potter may be contacted on VHF-FM radio channels 13 and 16. Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made with the Dredge Potter.

FOR THE DISTRICT ENGINEER:

//signed//

Andrew C. Schimpf, P.E.
Rivers Project Manager