Ohio River Louisville District Channel Maintenance Dredging McAlpine Lower Approach Ohio River Mile 607.5

Notice Number: 211472 / 2025-033
Effective: 07/28/2025 00:00 thru 08/06/2025 23:45 EDT

Notice is given that “Luhrs Bros., Inc” will commence channel maintenance dredging in the Ohio River at the McAlpine Lower Approach (Portland Bar), at Mile 607.5. Dredging operations will be conducted approximately 28 July – 06 Aug. 2025, 24 hours per day, seven days per week. During this period, the Dredge Bill Holman will be in the navigation channel and the disposal pipeline may be crossing the navigation channel, requiring the disposal pipeline to be opened for passing traffic. Contact the Dredge Bill Holman for passing instructions on marine channel 13. Once contact has been made with the Dredge Bill Holman, proceed at the slowest safe speed.

The dredge will be blocking one of the McAlpine lock chambers at a time during this work. Both chambers are 1200 feet long and at least one will remain in service at all times. Mariners shall take direction from the McAlpine Lock Operators regarding which chamber to use.

On approximately 03 Aug, the Ohio River will be closed to traffic at the McAlpine Lower Approach for a period up to 12 hours in length, to allow dredging operations to be uninterrupted during this time.

The contractor’s floating plant will consist of the Dredge Bill Holman, M/V’s LENARD and BUDDY, and the ROBERT T, one shop barge, one spill barge, and floating pipeline section. The Dredge Bill Holman, M/V’s LENARD and BUDDY will be monitoring marine channel 13.

//signed//
Kenney, Shawn M, Chief, Technical Support Branch