The Crosby is at Jonesville Lock, and Columbia Lock is being monitored. The Crosby should be back on the Red River July 1. At that point dredging will follow the schedule below. If Lock 5 becomes a bigger problem the dredge will start there and move south.

Mile 39 - 10 days
Travel to Lock 4 – 2 days
Lock 4 Touch up – 1 day
Travel to Westdale – 1 day
Westdale – 2 days
Lock 5 – 4 days
The Debuque Dredge should be back online mid-July.