All,

See today's update on Boggs, attached. BLUF: TVA is on site and cutting concrete. Approximately 60% of the concrete has been cut. We expect 2 more days of cutting concrete in a very confined space. No further damages have been reported. The Dredge Dubuque arrived at Boggs and is dredging the channel approach.

Next Navigation Call is scheduled for 23 OCT, Monday at 1000.
Dial in to (862) 799-9537

Emily Mott, Executive Director