RIAC – Rock Island District Mississippi River Winter Lock Closures – 2022/2023
RIAC - Rock Island District Mississippi River Winter Lock Closures - 2022/2023
As info…
Bernie Heroff
Many have been asking for the winter lock closure dates for the Upper Mississippi River. Below are the dates for the Rock Island District Locks plus Locks 24 & 25:
Lock 12: 13-Dec-22 to 3-Mar-23 (Dewater Chamber)
Lock 13: 14-Dec-22 to 6-Jan-23 (Upper Anchorage Replacement)
Lock 15 Main: 3-Jan-23 to 3-Mar-23 (Miter Gate #2 Machinery Repairs) – Auxiliary Chamber will be open.
Lock 19: 19-Dec-22 to 3-Mar-23 (Contract work)
Lock 21: 23-Dec-22 to 11-Jan-23 - 70’ width restriction and will be locking on the I-wall during this period– will also be closed from 0600-1700 during that time period (locking only at night) - helper boat required to pull cuts.
12-Jan-23 to 2-Mar-23 - Complete Lock Closure (Contract work)
Lock 22: 3-Jan-23 to 12-Jan-23 - 70’ width restriction - helper boat required
13-Jan-23 to 2-Mar-23 - Complete Lock Closure (Contract work)
Lock 24: Dates are not final but would be less than 45 days and will align with Locks 21, 22 & 25 full closures: approximatly 13-Jan-23 to 2-Mar-23 - Miter gate repairs and dewater lock.
Lock 25: Dates are not final but would be no more than 45 days and will align with Locks 21, 22 & 24 full closures: approximatly 13-Jan-23 to 2-Mar-23 – Lower guide wall repairs
Note, the official Nav Notices are pending for all locks / dates.
St. Paul locks, Mel Price Main chamber & Lock 27 Main chamber dates are still pending and we will get that out as soon as possible.
Thank you,
CASEY M. HERSCHLER
Canton Marine Towing Co.