RIAC – UMR Lock Openings Summary

A few have been asking as to how the winter lock work is going and if the scheduled openings were on track. RIAC inquired and so far and here is the current reports by Corps District with current scheduled opening dates: the work at Locks 3, 4, 12, 13, 15, 19, 21, 22, 24 & 25 are all on track to open as scheduled. If anything changes, RIAC will alert the group as soon as possible.

St. Paul District:

The work at Locks 3 & 4 is on schedule, if not a little ahead. At this point re-opening of the facilities should take place as scheduled, on March 13th. However, if things continue to go well, it could be up to a week earlier than planned.

Current scheduled opening dates:

  • Lock 3: 12 Mar 23
  • Lock 4: 12 Mar 23

Rock Island District:

Rock Island District Locks are on schedule. Lock 21 has a lot of work to go yet and will more than likely use the full closure.

Current scheduled opening dates:

  • Lock 12: 03 Mar 23
  • Lock 13: 03 Mar 23
  • Lock 15: 03 Mar 23
  • Lock 19: 03 Mar 23
  • Lock 21: 02 Mar 23
  • Lock 22: 02 Mar 23

St. Louis District:

St. Louis District Locks are on schedule.

Current scheduled opening dates:

  • Lock 24: 26 Feb 23
  • Lock 25: 26 Feb 23

Thank You,

Casey M. Herschler
Canton Marine Towing Company
Cell: 217.257.1749