Smithland Land and River Chambers Closures

Notice Number: 205101/2023-045
Date: 10/05/2023 11:07 thru 11/16/2023 11:07

Land (1200 ft) Chamber Closure: The Land Chamber will be closed from 5 October through 9 October 2023 for mooring of the Light Capacity Fleet (LCF) while preparing for work in the River Chamber. During this period, all traffic will utilize the River Chamber.

River (1200 ft) Chamber Closure: Following the Land Chamber closure, the LCF will move to the River Chamber. The River Chamber will be closed from 10 October through 16 November 2023 for the LCF to complete rehabilitation of the miter gate machinery. During this period, all traffic will utilize the Land Chamber.

//signed//

Shawn Kenney
Chief, Technical Support Branch