Total River Closure: Captain Anthony Meldahl Locks and Dam, Ohio River Mile 436.2
Notice Number: 201220/ 22-22
Date: 08/22/2022 07:00 thru 09/01/2022 05:00
Notice is given that on or about 22 August, 2022, the U.S. Army Corps of Engineers, Huntington District, will begin repairs to replace the motor control center of Captain Anthony Meldahl Locks and Dam Ohio River, Mile 436.2.
The auxiliary and main chambers will be closed no longer than 8 hours between 7:00 a.m. and 5:00 p.m. seven days per week, resulting in a total river closure. Both chambers will be available for lockage at 5:00 p.m. daily. It is anticipated this work will be completed on or about 1 September, 2022.
Mariners are urged to contact the lockmaster via marine radio on channel 13 for more information.
//signed//
KENT C. BROWNING
Chief, Technical Support Branch