Update – Meldahl L/D, Ohio River
10 July 2025
Meldahl L/D, Ohio River, Main Lock upper bulkhead slot installation. Auxiliary Chamber is available.
18 Lockages performed. Average delay (for tows locked in the last 24 hours) 33 hours 17 minutes. 12 tows in queue; 7 Upbound and 5 Downbound tows in queue.
Locking sequence is 3 Up and 3 Down. M/V Louise S is the first upbound lockage.
Dam discharge: 20’, Lower Gage: 16.1'
Main Chamber closed for upstream bulkhead slot installations. MW and RW dewatering boxes installed, concrete saw cutting ongoing.
Anticipate lockage delays in the Auxiliary Chamber until work is completed on or about 12 September 2025.
Thanks,
Domenico
Domenico Chianesi
Navigation Area Manager
US Army Corps of Engineers
Huntington District