Upper Mississippi: MISSISSIPPI RIVER MECHANICAL DREDGING (STRIKE REMOVAL) Buffalo Lower, UMR Mile 471.4-471.4
COMPLETED- Mississippi River Mechanical Dredging (Strike Removal) Buffalo Lower, UMR Mile 471.4-471.4
Notice number: 200976
Jon Klingman
Chief, Channel Maintenance Section Operations Division
____________________________
Amendment MISSISSIPPI RIVER - MECHANICAL DREDGING (STRIKE REMOVAL) - Buffalo Lower, UMR Mile 471.4-471.4
Notice Number: 200951/200933-1
Date: 06/10/2022 06:00 thru UNTIL FURTHER NOTICE
Mechanical dredging (Strike Removal) operations will commence on Thursday, 9-June-2022 and will continue until Further Notice at Buffalo Lower, UMR 471.4. Placement will be on the left descending bank at RM 472.8 to 473.0. Dredging will be performed 7 days per week, 12 hrs per day, 0600-1800.
Mariners are requested to contact the MV Laura K or MV Clee on channel 13 or 7, THIRTY minutes prior to transiting the area.
Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made.
//signed//
Jon Klingman
Chief, Channel Maintenance Section Operations Division
__________________________________
MISSISSIPPI RIVER
MECHANICAL DREDGING (STRIKE REMOVAL)
Buffalo Lower, UMR Mile 471.4-471.4
Notice number: 200933
Date: Effective 6/9/2022 07:00 until further notice
Mechanical dredging (Strike Removal) operations will commence on Thursday, 9-June-2022 and will continue until Further Notice at Buffalo Lower, UMR 471.4. Placement will be on the left descending bank at RM 472.8 to 473.0. Dredging will be performed 7 days per week, 10 hrs per day, 0700-1700.
Mariners are requested to contact the MV Laura K or MV Clee on channel 13 or 7, THIRTY minutes prior to transiting the area.
Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made.
//Signed//
Jon Klingman
Chief, Channel Maintenance Section Operations Division
Rock Island District